Fire Station 3 Remodel
This project will remodel Fire Station 3 to create more efficient, equitable, and safe work areas for Fire Department staff.
Status Updates
September 2023
This project is complete! Firefighters moved back into their newly renovated fire station in September 2023. We are excited to make use of our new, improved facility to serve the community.
October 2022
City leaders and Fire Department officials came together in late October to officially break ground on the $3.5 million renovation project. The station will be closed for about a year for an extensive interior remodel.
September 2022
Fire Station 3 closed in late September 2022 ahead of the planned remodel project. Firefighters and equipment were relocated to other fire stations in the city for the duration of the project, which is expected to take about 11 months. Read more about the project in this press release.
Background
The Fire Station 3 remodel was approved as part of the Citywide Facilities Project Priority Phasing Plan in June 2022. The project is paid for from federal American Rescue Plan Act (ARPA) funds. Construction is expected to start in the second half of 2022. Additional updates will be posted here.